| Tuesday, January 31: |
- AmeriCorps Rachel: Cedar St.
- Dismas Crew: Cedar St.
- Electrical Crew: 2310 W. Lee plugs & switches
|
| Wednesday, February 1: |
- AmeriCorps Rachel: Cedar St.
- Chuck's Team: 2400 W. Madison; 2401 Bank
- Dismas Crew: Cedar St.
- Framers: 716 E. St. Catherine prep crawl
- Holm Team: 1108 Plato Terrace cut parts, layout plates
- Trim Crew: 1740 Wilson punch & appliances
- Shawn Out
- Category 3 Review for 2213 St. Xavier @ 1:00 @ Old Jail
|
| Thursday, February 2: |
- AmeriCorps Rachel: Cedar St.
- Chuck's Team: 2400 W. Madison; 2401 Bank
- Dismas Crew: Cedar St.
- Dream Machine: 815 E. St. Catherine; 716 E. St. Catherine layout plates
- Framers: 716 E. St. Catherine joists & deck
- Holm Team: 1108 Plato Ter. cut parts, layout plates
- Trim Crew:
|
| Friday, February 3: |
- AmeriCorps Rachel: 2310 W. Lee paint
- Coakley w/Dismas: 2310 W. Lee paint
- Dismas Crew: 2310 W. Lee paint
- Dream Machine: 815 E. St. Catherine; 716 E. St. Catherine layout plates
- Framers: 716 E. St. Catherine deck, pour porches
- Layout Team: 2213 St. Xavier for dig; 4153 Wheeler for dig
|
| Saturday, February 4: |
- AmeriCorps Rachel: 1901 W. Madison demo
- Chuck's Team: 2400 W. Madison; 2401 Bank
- Coakley w/St. Matthews: 2310 W. Lee
- Dismas Crew: 1901 W. Madison demo
- Dream Machine: 815 E. St. Catherine
|